Friday, June 4, 2010

The asphalt patching inside the new curb line along Lehigh was completed on Thursday. The new curb line allows for some landscaped medians in the center of Lehigh as well as a longer and straighter right turn lane onto Glenview Road from Southbound Lehigh. We are coordinating schedules with the library work, and the new medians down the center of Lehigh should be done in the next week or two. The intersection pavement of Dewes and Washington will also be replaced later this month and may require traffic to be re-routed for several days (more details to follow).

The contractor began concrete pavement on the new Prairie cul-de-sac today. Weather pending, they plan to complete it tomorrow. After the concrete has time to cure, the area will be landscaped and then Prairie will be complete!