Tuesday, July 27, 2010

Washington-Dewes Intersection

The contractor is intending to replace the entire pavement in the intersection of Dewes and Washington Streets. The pavement will be removed and new high yield early strength concrete will be placed which requires a minimum cure duration of 72 hours before traffic can travel on the new pavement. The Village has coordinated this work with the summer school bus routes and the waste hauler to minimize the impact. The intersection will be barricaded and additional information signs will be posted one block away in each direction. The dates (weather dependent) selected for this work are August 4 (saw-cutting), August 5 (pavement removal) and August 6 (new pavement placement). The intersection will be reopened no later than August 10.

The Village appreciates everyone’s cooperation and patience during this project.